COMPLIANCE
- SUMMER 2004
|
|
|
In
2004 BRS began a major transformation from it's former self, both in function
and form. In May of 2004 Dave Pedroli was hired as NV Properties Manager
and I as Project Forman for construction of the Well House, the Genie
Shed, the Gazebo and the Shade Structures along side of the common
shop, what was to be a 3 month job. Everything was still located
on the 80 acres back then with very little organization. As I was constructing
the sheds and shade structures a separate contracted crew was building
the new yard and Metric, Jordan, Draka Sam and Dave were
busy clearing the 80 acres and moving everything into the new yard (see
80 acres below left). Just before the event that year BM bought the
Black Rock Saloon which was in quite a state of demise having not
been used in X many years. We did a Initial clean up of the place, ripped
out the orange shag carpet and did a little basic painting in the bar
area before opening the doors to DPW.
|
|